OSHA's Electrical standard for construction, 29 CFR 1926 Subpart K (1926.400 to 1926.449), sets requirements for electrical installations, equipment and work practices on construction sites. Electrocution is one of OSHA's "Focus Four" construction hazards, along with falls, struck-by and caught-in or caught-between hazards.
Construction sites present unique electrical risks: temporary wiring, extension cords dragged across wet ground, portable tools, overhead power lines and constant changes in the work area.
What Is the Construction Electrical Standard?
Subpart K is part of 29 CFR Part 1926. It is divided into four main areas: installation safety requirements, safety-related work practices, safety-related maintenance and environmental considerations, and safety requirements for special equipment. General industry employers follow Electrical Safety in General Industry in 1910 Subpart S.
Who Must Comply?
All employers engaged in construction work, including general contractors, electrical contractors, trades using power tools, and demolition and renovation contractors.
Key Requirements
Approved and examined equipment
Under 1926.403, all electrical conductors and equipment must be approved, and the employer must make sure equipment is free from recognized hazards likely to cause death or serious physical harm. Live parts operating at 50 volts or more must be guarded against accidental contact, and sufficient working space must be provided around electrical equipment.
Ground-fault protection
Under 1926.404(b)(1), employers must protect employees on construction sites by using either:
- Ground-fault circuit interrupters (GFCIs) on all 120-volt, single-phase, 15- and 20-ampere receptacle outlets that are not part of the permanent wiring of the building or structure and that are in use by employees, or
- An assured equipment grounding conductor program (AEGCP).
Assured equipment grounding conductor program
An AEGCP must include:
- A written description of the program, available at the jobsite.
- One or more competent persons to implement the program.
- A daily visual inspection of each cord set, attachment cap, plug and receptacle, and any equipment connected by cord and plug, before each day's use.
- Tests for continuity of equipment grounding conductors and correct attachment of the grounding conductor, performed before first use, before equipment is returned to service after repair, after any incident that could have caused damage, and at intervals not exceeding 3 months. Cord sets and receptacles that are fixed and not exposed to damage may be tested at intervals not exceeding 6 months.
- A record of the tests, maintained by logs, color coding or other effective means, until replaced by a more current record.
Damaged or defective equipment must not be used until repaired.
Temporary wiring and cords
Under 1926.405, temporary wiring is allowed during construction but must be removed immediately upon completion of the work. Flexible cords must be approved for hard or extra-hard usage, used only in continuous lengths without splice or tap (except for certain repairs), protected from damage, and not fastened with staples or hung in a way that could damage the insulation. Cords passing through doorways or other pinch points must be protected.
Safety-related work practices
Under 1926.416, employers must not permit an employee to work near any part of an electric power circuit that the employee could contact unless the employee is protected by de-energizing and grounding the circuit or by guarding it with effective insulation or other means. Before work begins, the employer must find out whether any part of an energized circuit is located where the work could bring a person, tool or machine into contact with it.
Lockout and tagging
Under 1926.417, controls that are to be deactivated during work on energized or de-energized equipment or circuits must be tagged, and equipment or circuits that are de-energized must be rendered inoperative and tagged.
Overhead power lines
Work near overhead power lines requires clearance, de-energizing or insulating barriers. Cranes and derricks follow specific power line rules in the cranes and derricks standard.
Penalties and Enforcement
Ground-fault protection, damaged cords, missing covers on boxes and exposed live parts are common construction citations. Electrocution hazards are frequently classified as serious. Maximum penalties are $16,550 per serious violation and $165,514 per willful or repeat violation in 2026.
Common Compliance Mistakes
- No GFCI protection and no documented AEGCP.
- Damaged cords repaired with electrical tape.
- Missing knockouts and covers on temporary panels.
- Cords run through doorways or under vehicle traffic without protection.
- Working near overhead lines without confirming clearance.
- Using ungrounded adapters to bypass grounding prongs.
How to Comply: Step by Step
- Choose GFCI or AEGCP. Most contractors use GFCIs for all temporary power.
- Inspect daily. Check cords, plugs and tools before each shift.
- Test and document. Test GFCIs, or perform and record AEGCP tests on schedule.
- Install temporary power correctly. Use approved panels, covers and cords.
- Survey for energized parts. Identify overhead and underground lines before work.
- Lock out and tag. Control circuits before work on equipment.
- Train workers on electrical hazards and safe practices.
How SMS360 Helps
SMS360's Audits & Inspections module supports daily cord and GFCI inspections and AEGCP test records on mobile devices. Training Management tracks electrical safety and competent person training, Lockout/Tagout procedures support circuit control, and Actions Management assigns fixes for defective equipment.
Frequently Asked Questions
Are GFCIs required on construction sites?
Yes, for temporary 120-volt, 15- and 20-amp receptacles in use by employees, unless the employer uses an assured equipment grounding conductor program.
How often must AEGCP tests be done?
Before first use, after repair, after suspected damage and at intervals not exceeding 3 months, or 6 months for fixed cord sets and receptacles not exposed to damage.
Can damaged extension cords be taped?
No. Cords with damaged insulation must be removed from service or properly repaired.
Does Subpart K apply to general industry?
No. General industry follows 29 CFR 1910 Subpart S.