A lift plan is a documented plan for a lifting operation using a crane, hoist or other rigging equipment. It identifies the load, the lifting equipment, the rigging, the people involved, the site conditions and the controls needed to complete the lift safely.
Many organizations require a basic lift plan for routine lifts and a more detailed critical lift plan for high-risk lifts. Crane incidents can be catastrophic, so planning is one of the most important controls in any lifting program.
When Is a Critical Lift Plan Needed?
There is no single OSHA definition of a critical lift, so companies set their own criteria. Common triggers include:
- Loads above a set percentage of the crane's rated capacity, often 75% or more.
- Lifts using two or more cranes.
- Lifts of personnel.
- Lifts over occupied buildings, live process equipment or public areas.
- Lifts near power lines.
- Loads that are unusually shaped, fragile or of high value.
- Blind lifts where the operator cannot see the load.
What to Include in a Lift Plan
- Load information: weight, dimensions, center of gravity and lifting points.
- Total load: load plus rigging, hook block and attachments.
- Crane information: make, model, configuration, boom length and radius.
- Capacity check: comparison of the total load with the crane's load chart at the planned radius.
- Rigging: slings, shackles, spreader bars and their ratings.
- Ground conditions: soil bearing, outrigger pads and underground hazards.
- Hazards: power lines, structures, wind limits and swing radius.
- Personnel: operator, rigger, signal person and lift supervisor, with qualifications.
- Communication: hand signals, radio channels and stop procedures.
- Sign-offs: review and approval before the lift.
OSHA Requirements That Apply
OSHA's Cranes and Derricks in Construction standard, 29 CFR 1926 Subpart CC, includes requirements for ground conditions, power line clearance, qualified riggers, signal persons, swing radius barricades and operator certification. Multiple-crane lifts require a plan developed by a qualified person under 1926.1432, and personnel hoisting has detailed requirements under 1926.1431. In general industry, overhead and gantry cranes have their own standard.
Common Mistakes to Avoid
- Forgetting to include rigging weight in the total load.
- Using the wrong load chart for the crane's configuration.
- Not verifying ground conditions under outriggers.
- Changing the lift on the fly without updating the plan.
- Skipping the pre-lift meeting.
How SMS360 Helps
SMS360's Work Permits module can manage lift plans and critical lift approvals alongside other permits, with required sign-offs before work starts. Training Management verifies operator, rigger and signal person qualifications, and Audit Management supports crane and rigging inspections.
Frequently Asked Questions
Does OSHA require a lift plan for every lift?
No. OSHA requires specific planning for certain lifts, such as multiple-crane lifts and personnel hoisting. Many employers require lift plans for all crane lifts as a best practice.
Who should prepare a critical lift plan?
A qualified person, such as a lift engineer or experienced lift supervisor, should prepare it, with review by the crane operator and site management.
What percentage of crane capacity makes a lift critical?
Company policies vary, but 75% of rated capacity is a common threshold.