EPA's Asbestos National Emission Standard for Hazardous Air Pollutants (NESHAP), 40 CFR Part 61 Subpart M, protects the public from asbestos released into the air during demolition, renovation, manufacturing, waste handling and disposal. For most businesses, the demolition and renovation provisions are the most important.
The Asbestos NESHAP works alongside OSHA's asbestos standards, which protect workers. Together they control both worker exposure and emissions to the outdoor air.
What Is the Asbestos NESHAP?
Subpart M sets work practice standards rather than emission limits. Most states and many local air agencies have been delegated authority to run the program, and some have stricter rules.
Who Must Comply?
Owners and operators of demolition or renovation activities at a facility, which includes institutional, commercial, public, industrial and residential structures, installations and buildings. Residential buildings with four or fewer dwelling units are generally excluded, unless they are part of a larger project, such as a group of homes demolished for a highway or commercial development. Both the building owner and the contractor can be considered owners or operators.
Key Requirements
Inspection before work
Before demolition or renovation, the owner or operator must thoroughly inspect the affected part of the facility for the presence of asbestos, including Category I and Category II nonfriable asbestos-containing material. Inspections are typically performed by accredited asbestos inspectors.
Regulated asbestos-containing material
Regulated asbestos-containing material (RACM) includes friable asbestos material and nonfriable material that has become or will become friable or will be subjected to sanding, grinding, cutting or abrading during the work.
Notification
Written notification must be provided to EPA or the delegated agency at least 10 working days before:
- Any demolition, even if no asbestos is present.
- Renovation involving RACM at or above the thresholds: at least 260 linear feet on pipes, 160 square feet on other facility components, or 35 cubic feet of facility components where the length or area could not be measured previously.
Emergency renovations must be reported as soon as possible, but no later than the following working day. Notifications must be updated if start dates or amounts change.
Work practice standards
- Remove all RACM from the facility before any activity that would break up, dislodge or disturb the material or block access to it.
- Keep RACM adequately wet during stripping and removal and until it is collected and contained for disposal.
- Carefully lower removed materials to the ground rather than dropping or throwing them.
- Use local exhaust ventilation and collection systems that do not cause visible emissions where wetting is not possible.
Trained supervision
At least one on-site representative, such as a foreman or management-level person, trained in the provisions of the NESHAP and the means of compliance, must be present during stripping, removing, handling or disturbing RACM. Refresher training is required every two years.
Waste handling and disposal
- Asbestos waste must be adequately wetted and sealed in leak-tight containers labeled with warning labels and the name and location of the waste generator.
- Waste must be disposed of as soon as practical at an approved waste disposal site.
- Vehicles used to transport asbestos waste must be marked during loading and unloading.
- A waste shipment record must accompany each load and be signed by the disposal site. If the generator does not receive a signed copy within 35 days, it must contact the transporter and disposal site, and report to the agency if not received within 45 days.
Penalties and Enforcement
EPA and delegated agencies inspect demolition and renovation sites and review notifications. Common violations include failing to inspect, failing to notify, dry removal and improper disposal. Civil penalties are assessed per day per violation and are adjusted for inflation, and knowing violations can lead to criminal prosecution.
Common Compliance Mistakes
- Skipping the asbestos inspection because a building is "too new."
- Forgetting that demolition notification is required even with no asbestos.
- Dry removal or allowing debris to fall and break.
- No trained representative on site.
- Unlabeled or torn waste bags.
- Missing waste shipment records.
How to Comply: Step by Step
- Inspect the facility for asbestos before demolition or renovation.
- Determine RACM amounts and compare them with thresholds.
- Notify the agency at least 10 working days before work starts.
- Hire qualified contractors and confirm a trained supervisor will be on site.
- Remove RACM first, keeping it adequately wet.
- Package and label waste in leak-tight containers.
- Track disposal with waste shipment records.
- Coordinate with OSHA requirements for worker protection.
How SMS360 Helps
SMS360's Compliance Management tools track inspections, notifications and project deadlines. The Document Library stores asbestos surveys, notifications and waste shipment records, Work Permits control work in areas with known asbestos, and Training Management records supervisor training and refreshers.
Frequently Asked Questions
Is notification required for demolition if there is no asbestos?
Yes. EPA requires notification at least 10 working days before any demolition of a regulated facility.
What are the renovation thresholds?
260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet where length or area could not be measured.
Do homeowners need to follow the Asbestos NESHAP?
Generally not for single homes or buildings with four or fewer units, unless part of a larger project. State and local rules may still apply.
How long must waste shipment records be kept?
Generators and disposal sites must keep waste shipment records for at least 2 years.